Operator at the control pendant of a JUGAO press brake

Delivery & support

From our floorto yours.

Who does what between the deposit and a running machine, and what happens after it runs.

Process

Three hand-offs,
one line.

The order runs as one line from our floor to yours. It bends wherever the owner changes, so you always know who is holding it.

Build time · working days from the deposit

80–160 t standard

25–35+10–15

200 t+, all-electric, tandem

40–55

Typical ranges. Your committed date is the one on the production schedule confirmation. The hatched extension applies with a DELEM DA-69T, a raised open height or custom tooling. From 200 t up you get a bilingual shop-floor briefing with the serial number every 7 working days.

If the date moves

Trigger
A supply or process issue expected to delay delivery 3+ days.
Notice
At least 7 working days before the milestone.
In writing
A lead-time letter and recovery plan from the delivery manager.
Major delay
Taken to the general manager: compensation or an alternative.

Site readiness

Ready the floor
before it ships.

Power, foundation, door and lifting, per model. Power, civil work and lifting are yours; we supply the drawings and guidance, and both sides sign the site survey form.

Power
AC 480 V, 3-phase, 60 Hz (220 V optional)
Main motor
7.5–11 kW, ≈18 A at 480 V
Weight
≈7.5 t
Concrete
≥250 mm thick, ≥3,000 psi
Lifting
Crane rated ≥1.5× machine weight (≥12 t), or an 8–10 t long-fork forklift

DoorClear opening ≥3.8 m high and ≥3.5 m wide for 100–200 t.

YoursPower, civil work and lifting, on site and at your cost.

OursInstallation drawings and guidance; the site survey form is signed by both.

Shipping

Every box
on paper.

Six documents on fixed dates, and a sealed-container report within 24 hours of loading. Each record carries the container and seal numbers. No compliance claim goes beyond what has been checked.

DocumentWhenWho

Proforma invoice & contractModel, configuration version, Incoterm, payment.

Before signing and the deposit

JUGAO sales, finance

Commercial invoice & packing listHS code (e.g. 8462.29), value, weights, case numbers; matched to the export declaration.

Within 2 working days of loading

JUGAO logistics, finance

Bill of lading or telex releaseConsignee is you or your broker on FOB or CIF.

3–5 working days after sailing; released once the balance is paid

Our forwarder

ISF (10+2) dataRequired by US customs; late filing draws CBP penalties.

At least 48 h before sailing

Data from us, filed by your broker; our agent on DDP

IPPC mark or fumigationOn solid-wood pallets and crates; plywood cases are exempt.

With the loading papers

JUGAO logistics

Certificate of origin & test certificateNo zero-duty claim is made.

With the originals, after the balance

JUGAO logistics, quality

Container No.Seal No.
  • Double cross lashing, wire-rope tensioners and timber wedges
  • Anti-rust oil, VCI film and a sealed foil bag with desiccant
  • Tools, foot switch and accessories in numbered plywood cases
  • Container and seal numbers on every record

Loading report · within 24 h

  • Empty container check
  • Machine in, base lashing close-ups
  • Packing list matched to case numbers
  • Doors shut, seal close-up
  • Telex release or release letter, once the balance is paid

Installation

Who lifts,
who powers up.

Unloading and placing are yours. Levelling, wiring checks and power-up are guided by us: remote video guidance is free, an engineer on site is an option.

You

Unload the container

Your forklift, truck crane and rigging crew. Finish inside the container free time; demurrage after that is yours.

You

Lift and place

Lift to our centre-of-gravity lifting drawing. Site lifting safety and third-party insurance sit with you and your rigging crew.

JUGAO

Level, wire, power up

Remote video guidance, free of charge. An engineer in the US is optional: return flights, lodging and day rates as set in the contract.

Ready for power-up?

Tick what is done on your site.

Book the power-up

If our engineer waits on a site that is not ready, the idle time is billed to you.

Training

Three ways
to learn it.

Live online training is the standard. Training at our factory is free; an engineer training your crew in the US is an option.

At our factory

2–3 working days

Who
Operators, process staff, maintenance
Covers
Controller programming, tool set-up, bend calculation, safety laser alignment; hydraulic and servo checks, common alarms
Language
Chinese or English with a technical interpreter; English manual and chaptered HD videos
Cost
Free; your team's travel is yours

Live online · standard

2 × 2 h live sessions

Who
Your operators
Covers
Start-up, parameter setting, first-part bending, live questions
Language
English over Zoom, Teams or WhatsApp video, with English documents
Cost
Included after power-up, usable for 12 months

At your plant · option

3–5 working days

Who
Your whole crew, on your own parts
Covers
Programming on parts in production, multi-bend optimisation, a hands-on test for every operator
Language
English, directly or with an interpreter; signed attendance and acceptance form
Cost
Travel, lodging and day rates as set in the contract; includes installation time

Warranty

Two clocks,
first to stop.

14 months from the bill of lading date or 12 months from acceptance at your plant, whichever ends first. Slide to the month your machine is accepted.

B/L date

14 months

Accepted

12 months
Accepted 3 months after the B/L: cover ends 14 months after the B/L, on the B/L clock.

When something stops

4 h

Ticket. Email, WhatsApp or the remote diagnosis module. An engineer replies within 4 h on working days, 12 h otherwise.

48 h

Parts. Once a hardware fault is confirmed, the replacement ships by DHL or FedEx.

Covered

Defects in manufacture or in the parts themselves, including main cylinders, frame, servo motors, controller and hydraulic valve blocks. New parts free of charge, with remote support. The failed part is returned, or photographed destroyed, as we instruct.

Not covered

  • Wear parts: upper and lower tools, urethane film, seals, filters, fuses, indicator lamps, hydraulic oil
  • Burn-out from the wrong oil grade, a lost phase or unstable voltage
  • Pressing past rated tonnage, removed safety devices, or system parameters changed without approval

Spare parts

Shipped from
Nantong.

Wear and electrical parts are stocked at our factory; core parts are ordered in. No US warehouse at present. Times below are references, not guarantees, and depend on customs.

In stock

Wear & electrical

Central parts store, Nantong factory

Hydraulic seal kits, high- and low-pressure filters, foot switches, emergency stops, proximity switches, standard relays, standard 835 mm segmented tools.

Out
24–48 h after the ticket is confirmed
Transit
DHL or FedEx, 4–7 working days door to door

Ordered in

Core & custom

From the original maker, or built to order

DELEM controller main boards, precision linear scales, model-specific proportional servo valves, custom non-standard long tools.

Restock
7–15 working days, inspected on arrival
Then
International air freight to you

Engineering review

Send a drawing.
Get an engineer.

Standard selections answered within 4 hours. Parts outside the rules get a written process review within 24 hours.

  • Part drawing: DXF, DWG, STEP or PDF
  • Material and thickness
  • Longest bend or cut length
  • Yearly volume

Write to info@ntjugao.com or message the factory on WhatsApp +86 132 2211 1178.

Drawings (DXF, DWG, STEP, PDF): attach them to an email to info@ntjugao.com, quoting your name.